25 May 2012

Taylor Woodrow site office complex will be operational by the end of June 2012. The park and ride site will be used as the main compound and storage area for the project.

Diversion of existing services in the verge of Toton Lane (including 33kV cables) has started and will continue throughout the summer 2012.

BT & Virgin Media cables at Bardill’s Island will be diverted in the summer 2012.

Now that the new play park at Eskdale Drive is complete the existing services can be diverted the diversions continue throughout 2012

The final water supply diversion in the Eskdale Drive and Inham Road area will be completed in Spring 2013

Service diversions will take place at all locations between the College and Eskdale Drive during 2012

Work starts to realign the culvert at Richmond Court at the end of the year and will take about 6 months to complete

Work to realign and culvert the brook between Eskdale Drive and Bramcote Lane are currently due to begin in September 2012 for about 5 months