29 May 2012

The works to the Toll Bridge will begin in late summer with refurbishment to the brick arches. There will be some overnight & weekend closures of the bridge for heavy lifting work.

The removal of the rail embankment between Coronation Avenue and the river is to start in July 2012. Removal of the old rail embankment between Coronation Avenue and Compton Acres is due to start in August and be complete by October 2012.

Service diversions on Coronation Avenue have started. Service diversions at Wilford Lane start summer 2012.

Temporary service diversions at Ruddington Lane begin in summer 2012. Ruddington Lane will be closed for three months from October 2012.

Access tracks and site compounds in Farnborough Road will be set up in October 2012. Three buildings on Farnborough Road will be demolished in July 2012.